127 FERC ¶ 62,237
FEDERAL ENERGY REGULATORY COMMISSION
|
|
Project No. |
1490-049 |
ORDER DENYING REQUEST TO CHANGE PROJECT BOUNDARY
(Issued June 25, 2009)
1.
On March 6, 2009,
Brazos River Authority (Brazos), licensee for the Morris Sheppard Dam
Hydroelectric
Project No. 1490, filed an application requesting Commission
authorization to change
the project boundary to remove approximately 335 acres of
buffer strip
land along the shoreline of Possum Kingdom Lake from the project
boundary, and
as mitigation to add another 930 acres of land to the project boundary
for
public recreation. The
project is located on the
BACKGROUND
2.
A new license for the Morris Sheppard Dam
Project was
issued on September 14, 1989.[1] Brazos currently owns almost all of the land
within the project boundary, including approximately 310 miles of
shoreline around
the project reservoir,
3. Of the 310 miles of shoreline, approximately 55 miles is leased to residential lessees. During the term of the previous license, the licensee filed revisions to the exhibits R and K requesting to remove from the project boundary all lands designated in the approved recreational use plan as existing or future cottage lease sites. By order issued May 15, 1980, in response to that request, the Commission required Brazos to “retain within the project boundary along the entire shoreline of any cottage site lease area in which…development has already occurred, a shoreline control strip at least 25 feet wide, measured horizontally from the edge of the reservoir at the normal maximum surface elevation of 1,000 feet m.s.l.”[2] The Commission decided specifically to retain this portion because removing those lands from the project boundary would make it difficult for the licensee and Commission staff to administer the license and, moreover, would not be sufficient to ensure the adequate protection of “the scenic, aesthetic, public recreation, and other environmental values of the reservoir shoreline.”[3] When the project was relicensed in 1989, Article 409 retained the requirement to maintain a buffer strip along the shoreline cottage sites.[4]
4.
On August 27, 2008, Brazos filed a petition
for a
declaratory order in which it stated that the
5.
The Commission issued an order responding
to
6. On October 20, 2008, the Possum Kingdom Lake Association, Custard/Pitts Land and Cattle Co., LP, and Costello Island, Inc. (Lessees), which lease lands in the project area, filed a request for clarification or, in the alternative, rehearing of the September 18 order. On November 20, 2008, the Commission issued an order on clarification in which it responded to specific questions posed by the Lessees.[7] Among other things, the Commission confirmed that a determination under the Federal Power Act as to what lands are required for project purposes and what type of property ownership by a licensee is acceptable is case-specific. The Commission also confirmed that the statement “it appears unlikely that we would grant an application to remove [leased] lands from the [project] boundary” was not based on a review of facts specific to the Lessees’ lands and is not a determination that those lands are needed for project purposes. In addition, the Commission confirmed that Standard Article 5 does not require all lands within the project boundary to be held in fee, and that the project license does not specifically prohibit the sale of fee ownership of project lands. However, the Commission pointed out that, pursuant to Standard Article 5, Commission authorization is required prior to the alienation of project lands.
LICENSEE’S APPLICATION
7.
According to the application, the
residential lessees along
the 55 miles of the reservoir’s shoreline have constructed
improvements,
including cottages and large homes, adjacent to or partially within the
project
boundary. The licensee requests removal
of approximately 335 acres of buffer strip land along this 55 miles of
shoreline from the project boundary,[8]
and as mitigation
for taking land out of the project boundary, to add another 930 acres
of land to
the project boundary for public recreation.
A 280-acre parcel of the 930 acres would be sold to the
8.
According to the licensee, the Texas
Legislature is
planning to enact legislation that would require Brazos to sell land
currently
owned at the cottage lease sites around
9.
Under the licensee’s proposal, the project
boundary
line would be redrawn at the maximum normal reservoir elevation of
1,000 feet
m.s.l., so that the land within the existing 25- or 50-foot-wide buffer
area adjacent
to existing cottage lease areas would be removed from the boundary.
10.
The licensee states that the buffer lands
are not
needed for project purposes, specifically recreation, since it is
difficult for
members of the public to access the buffer strip due to the numbers of
residences,
boat docks, and similar structures located close to the reservoir. The licensee further states that retaining
the buffer strip within the project boundary is not necessary to
control
activities that may cause erosion along the shoreline since
11.
Brazos states that its proposed change in
the project
boundary is in the public interest because it would not adversely
affect
project resources, would increase land available for public recreation,
should
not result in any adverse environmental impacts, and would
substantially reduce
MOTION TO INTERVENE AND COMMENTS
12.
On April 21, 2009, Costello Island, Inc. (
13.
In its June 17, 2009 filing, Costello
Island also
requests that the Commission make a determination that certain lands on
Costello
Island are also not necessary for project purposes, that those lands
need not
be retained in the project boundary, and that no further lands would
need to be
added to the project boundary if the Costello Island lands were removed
from
the project boundary. However,
14.
DISCUSSION AND
CONCLUSION
15.
Project boundaries
are used to designate the geographic extent of the lands, waters, works
and
facilities that the license identifies as comprising the licensed
project and
for which the licensee must hold the rights necessary to carry out
project
purposes. Project purposes include
operation and maintenance, flowage, recreation, public access,
protection of
environmental resources, and shoreline control, including protection of
shoreline aesthetic values.[10]
16.
The
primary issues to be weighed under the licensee’s proposal are,
first, whether
or not the lands proposed for removal from the project boundary are
necessary for
project purposes, and second, if they are, whether the lands proposed
for
addition to the project boundary would adequately mitigate the effects
of
removing the existing lands. As
mitigation for removing the 335 acres, the licensee proposes to add 930
acres
of land to the project boundary.
However, the licensee plans to sell a 280-acre parcel of the
proposed
930 acres to the TPWD. Commission policy
requires a licensee to retain any lands needed for project purposes. Because ownership of these lands would not be
retained by the licensee, no actions with respect to the continuing use
of
those lands could be made requirements of the license.
Consequently, the lands could not be included
in the project boundary, and their transfer to the TPWD could not be
considered
mitigation for the removal of the 335 acres.
Therefore, only the four parcels totaling 650 acres that would
continue
to be owned by
17.
18. The licensee indicates that it will maintain necessary control of the buffer lands through the issuance or permits and the Declaration placed on the lands to be sold and removed from the project boundary. However, once these lands are outside of the project boundary, the Commission would have no control or enforcement mechanism to ensure project purposes are met (e.g., buffering the project and reservoir from impacts due to vegetation removal, erosion, unauthorized activities, etc). In addition, while it may seem that all of the control issues are covered under the licensee’s current permitting system and the Declaration, we cannot foresee all of the circumstance that might warrant additional or different management activities on the buffer strip lands. These lands are directly adjacent to the reservoir, and as such any activity on this land has a unique ability to directly impact the project and reservoir.
19. In fact, the licensee’s proposal to include each specific provision of the Declaration indicates that the licensee fully understands the importance of these buffer lands. Several of the covenants (e.g., prohibiting clearing of vegetation) reserved in the Declaration concern specifically-stated project purposes, such as erosion control, flowage, and shoreline control.
20.
Generally, adding acreage to the
project
boundary is in the public interest, and adding approximately 21 miles
of trails
on the 650 acres proposed for inclusion in the project boundary would
unquestionably increase the project’s public recreational resources.[11] However, it appears that portions of the
proposed trail system have been completely or partially constructed,
and are
therefore already providing benefits to the public.
Including them in the project boundary would
provide federal control and allow them to be considered a project
resource, but
otherwise would not provide a great public benefit over and above what
is
already being provided, since the trails are being built and open to
the public
regardless of whether or not we include them in the project boundary.[12] In addition, past recreation monitoring
reports indicated that the number and types of facilities and
opportunities
provided by the licensee were sufficient to meet recreation demand at
the
project. So, while the licensee’s
proposal to add lands is generally positive, it does not meet any
specifically-identified recreational need at the project.
21.
Licensees are responsible for operating and
maintaining
projects in accordance with license requirements and project purposes,
including public recreation and environmental and shoreline protection. As development and multiple uses of the
shoreline continue to grow over the license term, it is expected that
licensees
may face increasing challenges related to such development.
22.
In its filing,
The Director orders:
(A) Brazos River Authority’s application, filed March 6, 2009, for Commission authorization to change the project boundary for the Morris Sheppard Dam Hydroelectric Project No. 1490, is denied.
(B) This order constitutes final agency action. Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F. R. §385.713.
Joseph D. Morgan
Director
Division of Hydropower
Administration and Compliance
[1]
[2]
[3]
[4] Brazos River Authority, 48 FERC ¶62,190 at 63,238.
[5]
[6] Id at P 10.
[7] Brazos River Authority, 125 FERC ¶61,193.
[8]
The lease areas include land owned by
[9] This trail system is not part of the licensee’s existing recreation plan.
[10] South Carolina Public Service Authority, 7 FERC ¶61,148 (1979).
[11]
If
these lands were put into the project boundary, license Articles 407
and 408
would require consultation with the U.S. Fish and Wildlife Service
(FWS) and
the Texas State Historic Preservation Officer (SHPO) prior to any
further
ground-disturbing activity on those lands.
[12] Project recreational resources include boat docks, swimming areas, camping units, restrooms, and picnic sites at eight different locations around the reservoir.
[13] AmerenUE, 117 FERC ¶ 31,301 (2006).
[14]
In its comments supporting the change in the project boundary,